| Spring 2003 |
Visit by Ron Baker |
Steering Committee |
Feb. 25 |
| |
Steering Comm. Meeting
(Initial Planning Meeting)
|
Steering Committee |
Mar. 12 |
| |
Subcommittee Planning Sessions/Stage #1 What
do we have/need? |
Chairs/Co-Chairs
Standards I-IX |
March-Mid-May |
| |
Develop Communication Strategy |
Comm. Committee |
March-Mid-May |
| |
Completed Stage #1 Templates Due to Deena |
Standard Chairs |
May 15 |
| |
Stage #1 Workshop Day
Stage #2 Implementation Discussion |
Steering Committee |
May 20 |
| |
|
|
|
| Summer 2003 |
Pilot Standard I |
Standard I/Steering Comm. |
Summer |
| |
Steering Committee Meeting
(Stage #2 Planning) |
Steering Committee |
July |
| |
Finalize Stage #2 Strategy |
Standards I-IX |
June-Aug |
| |
|
|
|
| Fall 2003 |
Campus Wide Kickoff |
Steering Committee |
Aug. 18 |
| |
Stage #2—Data Collection
Pre-Analysis of Data |
Chairs/Co-Chairs
Standards I-IX |
Aug-Nov |
| |
Stage #3—Reporting Data/Analysis |
Standard Chairs |
Nov-Feb |
| |
Steering Committee Meeting
(Status Check on Stage #3) |
Steering Committee |
Dec |
| |
|
|
|
| Spring 2004 |
Stage #3 Data Report Due to Deena |
Chairs |
Feb. 2 |
| |
Stage #4 Synthesis of Data |
Chris/John/Deena |
Feb. 2-March 15 |
| |
First Draft Distributed to Chairs (Narrative) |
Chris/John/Deena |
March 15 |
| |
First Draft due back to Deena |
Chairs |
April 15 |
| |
Reading Retreat
Stage #5—What’s missing? |
Steering Committee |
May |
| |
|
|
|
| Summer 2004 |
Supplemental Data Collection to correct omissions |
Steering Committee |
June-Aug. |
| |
Independent Review of Self-Study |
Review Team |
Sept. |
| |
|
|
|
| Fall 2004 |
Final Revisions of Standards Due to Deena |
Chairs |
October |
| |
Exhibit Collection |
Steering Committee |
October |
| |
Final Draft back to Chairs for Review |
Chris/John/Deena |
Nov |
| |
Final Review of Self-Study |
Steering Committee |
Nov |
| |
Form Implementation Committee |
Steering Committee
Administration |
Dec. |
| |
|
|
|
| Spring 2005 |
Final draft to printer |
Chris/John/Deena |
Jan. 15 |
| |
Campus Role-Playing Sessions |
Steering Committee |
Feb-Mar |
| |
Pre-visit Celebration |
Steering Committee |
April |
| |
Accreditation Team Visit |
Steering Committee |
April |
| |
Post-visit Celebration |
Campus Wide |
May |
| |
Implementation Committee
(Charge from President) |
Administration |
May |
| |
|
|
|
| Fall 2005 |
Implementation of Self-Study Suggestions |
Implementation Committee |
|
| |
|
|
|
| Spring 2006 |
Implementation of Self-Study Suggestions |
Implementation Committee |
|
| |
|
|
|
| |
|
Revised 3/11/03
|